Progress Updates:
- 6:50 AM J1 Web, myEMU, and J1 desktop are all available. IT will continue to solve problems over the next few days.
- 5:00 AM J1 Desktop 2023.2 Patch 1 is installed and available on RDS and staff computers that were connected to the network. J1 Web has not yet been upgraded.
- 2:20 AM DDU is no longer running hoping Jenzabar will soon confirm successful completion of this step. Kent is starting EMU permissions and customization steps
- 12:30 AM Still not making progress-sorry
- 10:45 PM still running data definition utility
- 10 PM currently running the data definition utility
- 8 PM Continuing J1 update to adjust database structure
- 6:20 PM Jenzabar
- 5:40 Create backup database
- 5 PM Volume snapshots started
There is a planned outage of the Student Information System (Jenzabar J1) on March 5th (Tuesday of Spring Break) from 5:00 PM to 3:00 AM on March 6th. myEMU will also be upgraded and will not be available 5:00 PM until 5:30PM and from 7:30PM and until 9:30PM on March 5th.
This outage is for J1 and myEMU. EMU payment processing (CashNET) is dependent on J1 and myEMU and will be down some during the J1 outage. The PowerFAIDS interface to J1 will not work during the upgrade. Other systems should not be affected.
If you use J1 Desktop, please quit J1 before leaving the previous week. If the client is running during the upgrade, you may need to restart your computer after the upgrade for J1 to work correctly.
We are updating to J1 2023.2 at this time because the J1 2022.2 version we are currently running is nearing its end of life.